2015
December 3
We are home!
November 25
Gas furnace on, warming the house
November 17
Kitchen cabinets, gas cooktop and plumbing finished
October 22
Wastewater system finished
October 14
Basic lighting installed throughout the house
September 30
Construction crane removed from cortile
September 22
Windows and doors finished, all bathroom plumbing
August 10
All flooring laid: new tiles and wood, old terracotta
July 9
Last exterior scaffolding removed
June 9
Chose and ordered all flooring
April 24
New roof tiles placed, roof finished
April 15
Ordered windows and doors
April 10
Works in progress: interior walls, W side enclosed, plumbing for heat system
February 20
Received estimates for windows and doors
February 5
Heavy snowfall!
January 30
New roof on