2015

  • First post
  • Second post
  • Third post
  • Fourth post
2015
We are home!
Gas furnace on, warming the house
Kitchen cabinets, gas cooktop and plumbing finished
Wastewater system finished
Basic lighting installed throughout the house
Construction crane removed from cortile
Windows and doors finished, all bathroom plumbing
All flooring laid: new tiles and wood, old terracotta
Last exterior scaffolding removed
Chose and ordered all flooring
New roof tiles placed, roof finished
Ordered windows and doors
Works in progress: interior walls, W side enclosed, plumbing for heat system
Received estimates for windows and doors
Heavy snowfall!
New roof on